2010年P(guān)MP美國項目管理考試習(xí)題及答案三十三
QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ .
A Project specification tree.
B Customer's deliverable list.
C Customer's milestone dates.
D Work breakdown structure.
E Listing of customer team meeting dates.
參考答案:D
QUEST The critical path in a network is the path that:
A Has the greatest degree of risk.
B Will elongate the project if the activities on this path take longer than anticipated.
C Must be completed before all other paths.
D All of the above.
E A and B only.
參考答案:B
QUEST The major difference between PERT and CPM networks is:
A PERT requires three time estimates whereas CPM requires one time estimate.
B PERT is used for construction projects whereas CPM is used for R & D.
C PERT addresses only time whereas CPM also includes cost and resource availability.
D PERT requires computer solutions whereas CPM is a manual technique.
E PERT is measured in days whereas CPM uses weeks or months.
參考答案:A
QUEST A calendar that identifies when a project may be performed on an activity is called a:
A Project calendar.
B Resource calendar.
C Milestone point.
D Key point.
E Work unit.
參考答案:A
QUEST Planning activities such that predetermined resource availability pools are not exceeded is called:
A Resource leveling.
B Manpower leveling.
C Resource limited planning.
D Manpower planning.
E Manpower contingency planning.
參考答案:C