2010年P(guān)MP美國項目管理考試習題及答案二十八
QUEST On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850.  Calculate the schedule variance: 
A ¥-100 
B ¥100 
C ¥-150 
D ¥150 
E 85% 
參考答案:C
QUEST A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks.  Calculate the variance: 
A 1.50% 
B 33.00% 
C 75% 
D 67% 
E None of the above. 
參考答案:B
QUEST Resource leveling will often affect the project by making it: 
A Shorter. 
B Longer 
C More responsive to customer needs. 
D A and C 
E B and C. 
參考答案:B
QUEST Using the figure in the Special window,  The slacktime in Activity "G" is _____ weeks. 
A 2 
B 3 
C 4 
D 5 
E 7 
參考答案:C

QUEST Using the figure in the Special window,  Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks. 
A 2, 10 
B 4, 12 
C 6, 14 
D 7, 15 
E 9, 17 
參考答案:A