成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓
當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
2010年P(guān)MP美國項目管理考試習題及答案十八
QUEST The WBS is:
A An organization oriented family tree of the project.
B A task oriented family tree of the project.
C A cost centered structure of the project.
D Only required on large complex projects where separately identifiable work packages are difficult to construct.
E None of the above.
參考答案:B
QUEST Including the customer in the process of project planning is:
A Slow and counterproductive.
B Essential in the definition and documentation of project goals.
C Necessary, but of limited value.
D Unnecessary because project goals are defined in the proposal stage.
E None of the above.
參考答案:B
QUEST The scope management provides:
A A basis for future decisions about the project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above.
E B and C only.
參考答案:D
QUEST During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
A Ask the line manager to make the decision.
B Ask the line manager to work with senior management to prioritize the work.
C Ask your sponsor to meet with the line manager.
D Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E Prepare a purchase order to outsource the work.
參考答案:D
QUEST Proper implementation of project management will guarantee that:
A Budgets will be met.
B Schedules will be adhered to.
C Quality/performance will be met.
D The project will be a success.
E None of the above.
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案十七
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3