QUEST Documented work authorization provide:
A a means of effective internal coordination of the project's activities.
B an audit trail of all work authorized from project initiation to completion.
C a means for communication of work activity between the project manager and the performing activities.
D All of the above
E A and B only.
參考答案:D
QUEST The project life-cycle can be described as:
A project concept, project planning, project execution, and project close-out.
B project planning, work authorization, and project reporting.
C project planning, project control, project definition, WBS development, and project termination.
D project concept, project execution, and project reporting.
E All of the above.
參考答案:A
QUEST A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
參考答案:D
QUEST Scope Management:
A entails managing the project's work content.
B is a subset of configuration management and as such is performed by CM specialists.
C is concerned with naming all activities performed, the end products which results and the resources consumed.
D is not a concern of the project manager.
E None of the above.
參考答案:C
QUEST Feasibility studies occur in which life cycle phase (s)?
A Conceptual
B Conceptual or Development
C Execution
D Preliminary planning
E any life cycle phase
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案十三
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)