2010年PMP美國項目管理考試習題及答案二十五
QUEST A(n) _____ is defined as a specified accomplishment  in a particular instant in time which does not consume time or resources. 
A Activity 
B Event. 
C Correlation 
D Constant 
E Event constrained within planned effort. 
參考答案:B
QUEST Which of the following impacts the critical path? 
A Changing the task duration. 
B Reduce the free float of an activity. 
C Executing a backward pass 
D A or B 
E None of the above. 
參考答案:A
QUEST The range of time allowed for an activity to be completed in is the _____. 
A Planned time (Duration). 
B Float time (LS - ES, or LF - EF). 
C Critical time (when ES = LS, or EF = LF). 
D Scheduled time (LF - ES). 
E Event. 
參考答案:D
QUEST Free float is the amount of time that an activity may be delayed with out affecting the _____. 
A Early start of the succeeding activities. 
B Late start of the succeeding activities. 
C Project finish. 
D Cost of the project. 
E None of the above. 
參考答案:A

QUEST Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration. 
A 0.5 
B 1 
C 1.8 
D 2.2 
E 2.8 
參考答案:C