2010年P(guān)MP美國項目管理考試習題及答案四十四
QUEST Using the situation stated in the Special window,  what is the total variable costs for producing one widget? 
A ¥1,020 
B ¥1,010 
C ¥1,015 
D ¥20 
E None of the above. 
參考答案:E
QUEST A technique that can be used to measure the total income of a project compared to the total moneys expended at any period of time is: 
A return on investment (ROI) 
B net present value (NPV) 
C discounted cash flow (DCF) 
D B and C 
E All of the above. 
參考答案:E
QUEST Cost management includes processes that are required to maintain financial control of projects.  These processes may include: 
A economic evaluation 
B cost estimating 
C cost forecasting 
D B and C 
E All of the above. 
參考答案:E
QUEST Which of the following is considered a method of accelerated depreciation: 
A sum-of-the-years digit 
B straight-line 
C double-declining-balance 
D A and C 
E All of the above. 
參考答案:D

QUEST The Cost Performance Index is computed as: 
A budget cost of work performed divided by actual cost of work performed 
B budget cost of work performed minus actual cost of work performed 
C budget cost of work performed minus budget cost of work scheduled 
D budget cost of work scheduled divided by  budget cost of work performed 
E actual cost of work scheduled divided by  budget cost of work performed 
參考答案:A