2010年PMP美國項目管理考試習題及答案五十
QUEST The salvage value of an asset is: 
A The value of the scrap metal if a new asset were taken to a scrap yard. 
B The value that an asset has on the books after one year of depreciation. 
C The costs that have been sunk into the project to date. 
D The expected cash value at the end of an assets useful life. 
E A and D only. 
參考答案:D
QUEST The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by: 
A Multiplying the actual hours worked on the project by the budgeted labor rate. 
B Multiplying the budgeted hours to complete the task by the budgeted labor rate. 
C Dividing the actual hours required to complete the task by the budgeted labor rate. 
D Cannot be determined. 
E None of the above 
參考答案:B
QUEST The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called: 
A Feasibility studies. 
B Bills of materials. 
C Pert charts. 
D Managerial reserves. 
E None of the above 
參考答案:A
QUEST The planned cost for the total project at its inception is called the _____. 
A Cost of goods sold. 
B Depreciable value. 
C Budgeted cost. 
D All of the above. 
E B and C only. 
參考答案:C

QUEST Which of the following is not a measure of the profitability of a project or program? 
A Return on original investment. 
B Net present value. 
C Depreciation. 
D Discounted cash flow. 
E None of the above 
參考答案:C