2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案四十
QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____.
A establishing values for required functions
B provide the required functions at the lowest overall cost.
C identifies the required function of an item
D seeks to trade performance for cost
E None of the above.
參考答案:D
QUEST The ability to achieve cost savings is inversely proportional to _____.
A the earned value achieved to date
B the estimated costs to complete
C empowerment to the P.M.
D productivity
E None of the above.
參考答案:A
QUEST The estimated cost to complete (ETC) is _____.
A BCWP/ACWP
B the forecasted and final cost - cost to date
C (ACWP-BCWP)/BCWP * 100
D Total estimate - ACWP
E None of the above.
參考答案:B
QUEST Considering alternate suppliers is a form of _____.
A Value engineering.
B Risk Analysis
C Contract Management
D Project integration
E All of the above.
參考答案:A
QUEST You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:
A The project is operating at a favorable cost efficiency ratio.
B the project is spending more than planned
C the project is behind schedule
D the project is ahead of schedule
E B and C
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十九
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)