QUEST The lowest dollar amount 'at stake' is associated with the following phase of the project: 
A conceptual 
B execution 
C cut-over 
D post project evaluation 
E A and D only 
參考答案:A
QUEST The highest degrees of project risk and uncertainty are associated with the following phase of the project: 
A conceptual 
B execution 
C cut-over 
D post project evaluation 
E A and D only 
參考答案:A
QUEST Risk management allows the project manager and the project team to: 
A eliminate most risks during the planning phase of the project 
B identify project risks 
C identify impacts of various risks 
D plan suitable responses 
E B, C and D only 
參考答案:E
QUEST Since risk is associated with most projects, the best course of action is to: 
A cover all project risks by buying appropriate insurance 
B ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner. 
C avoid projects with clear and present risks 
D eliminate all known risks prior to the execution phase of the project 
E identify various risks and implement actions to mitigate their potential impact 
參考答案:E
.jpg)
QUEST When items to be purchased for a project are specified by performance characteristics: 
A paperwork is greatly reduced 
B the supplier is held liable for the operation of the item 
C the supplier is held liable for the maintenance of the item 
D the supplier is held liable for that the item meets the design, dimensions, and tolerance specifications. 
E B and D only 
參考答案:B