2010年P(guān)MP美國項目管理考試習(xí)題及答案14
QUEST Pure Risk differs from Business Risks because Pure Risk's _____ . 
A include chances of both profit or loss associated with the business. 
B include chances of loss and no chances for profit associated with the business. 
C must incur personal loss with business liability. 
D must incur business liability associated with loss of pure profit. 
E B and C 
參考答案:B
QUEST Response Planning is the responsibility of the functional areas and considers 
A mitigation. 
B deflection. 
C contingency planning. 
D unforeseen occurrences. 
E All of the above. 
參考答案:E
QUEST Amount at Stake is the _____ . 
A function of planned time/real time project costs. 
B risk identified in successful project completions. 
C (Standard Project Deviation + Expected Costs)/6 
D cost of investment loss + least cost to restore status quo. 
E inherent risk at conception altered by standard project deviations. 
參考答案:D
QUEST The Delphi Method is _____ . 
A used to derive a consensus arriving at a convergent solution 
B useful in determining probability relating to future events. 
C used with questionnaires based on established scenarios. 
D continued as an iterative process until a solution is reached. 
E All of the above. 
參考答案:E

QUEST Risk Event Status is defined as _____ . 
A Risk Probability  x  Amount At Stake. 
B the severity of the consequences. 
C how likely the event is to occur with risk. 
D (Cost + Benefit + Business Risk) / Insurable Risk. 
E B and C 
參考答案:A