2010年PMP美國項目管理考試習題及答案16
QUEST Using the possible profit and loss outcomes shown in the Special window, find the expected profit (loss)
A ¥-1,000
B ¥1,000
C ¥2,000
D ¥1,200
E None of the above
參考答案:D
QUEST Contingency planning should include all but which of the following?
A The development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments.
B the development of schedule alternatives and work-around
C the management of a contingency budget
D an assessment of project shut-down liabilities.
E A and C
參考答案:A
QUEST During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
參考答案:A
QUEST Budgeted contingencies can be detemined by:
A past experience
B applying standard allowances
C detemining the sum total of the most probable variances of the various risk items properly identified.
D All of the above.
E None of the above.
參考答案:D

QUEST In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
A Work breakdown structure
B milestone review and schedule technique
C cost/schedule control system
D planning programming budget system
E program and evaluation review technique
參考答案:A