2010年PMP美國項目管理考試習題及答案七十
QUEST Affinity diagrams are used to:
A determine if a process is in control.
B determine root cause.
C show the relationship among variables.
D categorize large amounts of data.
E None of the above.
參考答案:D
QUEST Which quality management tool would be used to determine potential causes of a production problem?
A control chart.
B Ishikawa diagram.
C scatter diagram.
D histogram.
E run chart.
參考答案:B
QUEST Which of the following is not an input to quality planning?
A scope statement.
B regulations.
C work results.
D standards.
E quality policy.
參考答案:C
QUEST To determine what causes the majority of quality problems in a process, a very useful tool is the:
A cause and effect diagrams.
B flow chart.
C control chart.
D pareto chart.
E trend chart.
參考答案:D

QUEST For a given characteristic in a construction process, the standard deviation associated with production variation is 0.8", and the standard deviation associated with measurement variation is 0.6". The total standard deviation for this characteristic is:
A 1.4"
B 1.2".
C 1.0"
D 0.8"
E 0.2"
參考答案:C