2010年PMP美國項目管理考試習題及答案八十二
QUEST In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review? 
A Not working directly with the assigned functional employees 
B Employees spend only a short amount of time assigned to the project 
C Not being knowledgeable enough to evaluate employees on technical judgment 
D All of the above 
E A and B only 
參考答案:D
QUEST The behavioral responsibilities of a project manager may also include dealing with: 
A The public 
B Regulatory personnel 
C The legal environment 
D Environmental issues 
E All of the above 
參考答案:E
QUEST Which of the following fall(s) under the responsibilities of a project manager? 
A Labor relations with project personnel 
B Affirmative action 
C Personnel training 
D Discrimination and equal employment opportunity 
E All of the above 
參考答案:E
QUEST Team members want to work for a project manager that can provide them with career path planning.  In which organizational form is career path planning difficult for project employees? 
A Matrix 
B Pure project 
C Project coordinator 
D Project expediter 
E Classical/traditional 
參考答案:B

QUEST The Delphi Method is well-suited for: 
A Decision-making 
B Forecasting 
C Overhead rate estimating 
D All of the above 
E A and B only 
參考答案:E