2010年P(guān)MP美國項目管理考試習(xí)題及答案七十四
QUEST Most project management leadership theories focus on all of the following except: 
A  Personal characteristics of the project manager 
B The situation at hand 
C Personal traits of the subordinates 
D Behavioral styles of the project manager 
E Usefulness of authority and power in leadership 
參考答案:C
QUEST Which theory(s) prescribes a form of participative management? 
A theory X 
B theory Y 
C theory Z 
D A or B 
E B or C 
參考答案:B
QUEST In which of the following organization(s) does the Functional Manager have the LEAST authority? 
A coordinator 
B weak matrix 
C strong matrix 
D functional 
E expediter 
參考答案:C
QUEST Project team building is most difficult in which type of environment? 
A weak matrix organization 
B strong matrix organization 
C projectized organization 
D functional organization 
E expediter organization 
參考答案:A

QUEST The core function of the PM is 
A client interfacing 
B project integration 
C quality assurance 
D personal administration 
E All of the above. 
參考答案:B