2010年P(guān)MP美國項目管理考試習(xí)題及答案33
QUEST Which of the following is equivalent to a lump sum contract: 
A fixed price contract 
B price fixing contract 
C purchase order 
D All of the above. 
E B and C only 
參考答案:A
QUEST Which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party: 
A free on board 
B receipt for merchandise 
C packaging list 
D loading list 
E bill of lading 
參考答案:E
QUEST Which of the following is associated with a buyer's request for material to meet a particular need: 
A material warranty 
B material guarantees 
C implied warranty of salability 
D implied warranty of fitness for a particular purpose 
E A and C only 
參考答案:D
QUEST The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as: 
A post project evaluation 
B post contract evaluation 
C post mortem 
D procurement performance evaluation 
E contractor's performance evaluation 
參考答案:E

QUEST Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified: 
A beneficial completion 
B substantial completion 
C project completion 
D contract closeout 
E final completion 
參考答案:B