PMP美國項目管理模擬樣題2
to the problem was reached. During the meeting, the participants
started wondering why they thought the problem was such a big issue.
Sometime after the meeting, you received an e-mail from one of the
meeting members saying they’ve changed their mind about the solution
reached in the meeting and need to resurface the problem. The
solution reached during the initial project meeting is an example of which of the following conflict resolution techniques?
A. Confrontation
B. Forcing
C. Smoothing
D. Storming
在你的項目會議中,大家討論了一個問題,對這個問題的解決方案也已達成。在會議過程中,與會者起初不解他們?yōu)槭裁从X得這個問題是個大問題。會議后一段 時間,你收到了一封來自一名與會成員的電子郵件,信中說他們變了主意,不再同意會中達成的解決方案并要求重新討論這個問題。在項目啟動會議上達成的解決方案是下列哪項沖突解決技巧的一個例子?
A. 面對
B. 強制
C. 緩和
D. 集思廣益
2.You are the project manager for Heartthrobs by the Numbers Dating
Services. You’ ve working on an updated Internet site that will
display pictures as well as short bios of prospective heartbreakers.
You’ve just completed your project staff assignments and published
the project team directory. Which process are you in?
A.Resource Planning
B.Organizational Planning
C.Project Development Planning
D.Staff Acquisition
你是提供以心跳計數(shù)來測定年齡服務項目的項目經理。你目前正在籌建一個最新的網站來展示一些圖片以及一些可能引起心臟變化的激素。你剛剛完成對你項目成員的分工并公布了項目團隊成員的姓名地址名錄。你正處于哪個流程?
A.資源規(guī)劃
B.組織規(guī)劃
C.項目發(fā)展規(guī)劃
D.人員獲取
3.Each of the following describes an element of the Scope Definition
process except:
A.Breaking down the major deliverables of the project into smaller,
manageable components
B.Supporting detail
C.Decomposition
D.Improving the accuracy of time and cost estimates
下列每個選項都描述了范圍定義流程的一個要素,除了:
A.將主要的項目可交付成果分解為規(guī)模較小、易于管理的要素
B.詳細輔助資料(supporting detail)
C.分解
D.進一步精確時間和成本估算