PMP美國(guó)項(xiàng)目管理模擬樣題3
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1.You are a project manager for Waterways Houseboats, Inc. You’rebeen asked to perform a benefit/cost analysis for two proposed
projects. Project A costs $2.4 million with potential benefits of $12
million and future operating costs of $3 million. Project B costs
$2.8 million with potential benefits of $14 million and future
operating costs of $2 million. Which project should you recommend?
A. Project A because the cost to implement is cheaper than Project B
B. Project A because the potential benefits plus the future operating
costs are less in value than the same calculation for project B
C. Project B because the potential benefits minus the implementation
and future operating costs are greater in value than the same
calculation for Project A
D. Project B because the potential benefits minus the costs to
implement are greater in value than the same calculation for Project A
你是水路游艇公司的一名項(xiàng)目經(jīng)理。公司指派你對(duì)提議的兩個(gè)項(xiàng)目進(jìn)行成本/收
益分析。項(xiàng)目A需要耗費(fèi)的成本是240萬美元,潛在收益為1200萬美元,遠(yuǎn)期運(yùn)營(yíng)
成本為300萬美元。項(xiàng)目B需要耗費(fèi)的成本是280萬美元,潛在收益為1400萬美
元,遠(yuǎn)期運(yùn)營(yíng)成本為200萬美元。你將向公司推薦哪個(gè)項(xiàng)目?
A. 項(xiàng)目A,因?yàn)槠鋱?zhí)行成本比項(xiàng)目B少
B. 項(xiàng)目A,因?yàn)闈撛谑找婕由线h(yuǎn)期運(yùn)營(yíng)成本的價(jià)值總額比項(xiàng)目B少
C. 項(xiàng)目B,因?yàn)闈撛谑找鏈p去執(zhí)行成本和遠(yuǎn)期運(yùn)營(yíng)成本的價(jià)值額比項(xiàng)目A大
D. 項(xiàng)目B,因?yàn)闈撛谑找鏈p去執(zhí)行成本的價(jià)值額比項(xiàng)目A大
2.You’ve been assigned as project manager on a research and
development project for a new dental procedure. You’ve published the
scope statement and are working on the scope management plan. What is
the purpose of the scope management plan?
A. It describes and documents a scope baseline to help make future
project decision.
B. It decomposes project deliverables.
C. It describes how project scope changes will be incorporated into
the project and how project scope will be managed.
D. It describes how cost and time estimates can be composed for
project scope changes.
你被任命為項(xiàng)目經(jīng)理,來負(fù)責(zé)研究和開發(fā)一項(xiàng)新的牙齒治療程序的項(xiàng)目。你已經(jīng)
發(fā)布了范圍說明書并正在準(zhǔn)備范圍管理計(jì)劃。請(qǐng)問,范圍管理計(jì)劃的目的是什么?
A. 它描述和說明的是一個(gè)范圍基準(zhǔn)以有助于未來的項(xiàng)目決策。
B. 它是對(duì)項(xiàng)目可交付成果的分解。
C. 它描述的是項(xiàng)目范圍變更將如何融入到整個(gè)項(xiàng)目中去,以及項(xiàng)目范圍將如何
管理。
D. 它描述的是項(xiàng)目范圍變更過程中成本和時(shí)間估算要如何調(diào)整應(yīng)對(duì)。
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!