2010年PMP美國項目管理考試習題及答案三
QUEST The scope statement provides 
A A basis for future decisions about a project. 
B A baseline to accomplish verification measures. 
C A baseline to evaluate potential scope changes. 
D All of the above 
E B and C only 
參考答案:D
QUEST A work breakdown structure: 
A assures all work is identified. 
B subdivides the project into manageable segments. 
C provides the project sponsor with a time-phase task summary. 
D both A and B. 
E All of the above. 
參考答案:D
QUEST Budgetary estimates are the output of the _____ phase(s) of the project. 
A conceptual 
B development 
C implementation 
D finish 
E All of the above. 
參考答案:B
QUEST Which of the following are included in the Acquisition phase(s) of the project life cycle. 
A concept and development 
B development and planning 
C execution and phase-out 
D planning and implementation 
E concept and planning 
參考答案:C
.jpg)
QUEST The scope statement provides 
A A basis for future decisions about a project. 
B A baseline to accomplish verification measures. 
C A baseline to evaluate potential scope changes. 
D All of the above 
E B and C only 
參考答案:E