QUEST Typical characteristics of a work package include: 
A Representation of units of work at a level where work is performed 
B Clearly distinguishes one work package from all others assigned to a single functional group 
C Limits the work to be performed to relatively short periods of time 
D All of the above 
E A and B only 
參考答案:E
QUEST Problems can occur in properly defining a project because: 
A Project goals may not be agreeable to all parties 
B The plan was "too loose," thus allowing priorities to change 
C Low turnover of project personnel 
D Too much communication between the client and project personnel 
E The project objectives were quantified 
參考答案:A
QUEST In preparing a good project definition, experienced project managers will: 
A Concentrate mainly on the end product rather than costs or benefits. These come later. 
B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it. 
C Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change. 
D Try to convert objectives into quantifiable terms. 
E All of the above 
參考答案:E
QUEST Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____. 
A Preliminary planning, detail planning, closeout 
B Implementation, reporting, termination 
C Development, implementation, termination 
D Execution, reporting, finishing 
E Implementation, termination, post-audit review 
參考答案:C

QUEST The contractual statement of work (CSOW) 
A Must be the same as the proposal statement of work 
B Does not identify reporting requirements 
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work 
D Identifies the contractor's organizational structure for the project 
E All of the above 
參考答案: C