1 Work packages are used to: 
A Represent units of work at a level where work is performed. 
B Clearly distinguish one work package from all others assigned to a single functional group. 
C Limit the work to be performed to relatively short periods of time. 
D All of the above. 考試大論壇
E A and B only 
ans:D 
2 Project life cycles are very useful for _____ and _____ . 
A Configuration management, termination 
B Objective setting, information gathering 
C Standardization, control 
D Configuration management, weekly status updates 
E Approval, termination 
ans:C 
3 Which of the following are included as part of a scope statement? 
A Project justification 
B Project deliverables 
C Project objectives 
D All of the above 
E B and C 
ans:D 
4 The initial document that formally recognizes the existence of a project is the _____ . 
A Scope baseline 
B Management plan 來(lái)源:www.examda.com
C Project charter 
D Configuration control report 
E None of the above 
ans:C 
5 Which of the following is not a scope management process? 
A Initiation 
B Scope planning 
C Scope Definition 
D Scope change control 
E Scope verification 
ans:D 
6 In which of the following scope management processes is the scope management plan prepared? 
A Initiation 
B Scope planning 
C Scope Definition 
D Scope change control 
E Scope verification 
ans:B 
7 The project charter is prepared in which scope management process? 
A Initiation 
B Scope planning 考試大論壇
C Scope Definition 
D Scope change control 
E Scope verification 
ans:A 
8 The work breakdown structure (WBS) is first developed in which scope management process? 
A Initiation 
B Scope planning 
C Scope change control 
D Scope Definition 
E Scope verification 
ans:D 
9 In which of the following scope management processes are subject matter experts used? 
A Initiation 
B Scope planning 來(lái)源:www.examda.com
C Scope Definition 
D Scope change control 
E Scope verification 
ans:A 
10 A Work Berakdown Structure is most useful for: 
A Identifying individual tasks for a project. 
B Scheduling the start of tasks. 
C Developing a cost estimate. 
D Determining potential delays. 
E A and C. 
ans:E 
11 The scope statement provides 
A A basis for future decisions about a project. 
B A baseline to accomplish verification measures. 
C A baseline to evaluate potential scope changes. 
D All of the above 
E B and C only 
ans:D 
12 A work breakdown structure: 
A assures all work is identified. 
B subdivides the project into manageable segments. 
C provides the project sponsor with a time-phase task summary. 
D both A and B. 
E All of the above. 
ans:D 
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問(wèn)就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問(wèn)終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問(wèn)解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問(wèn)就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問(wèn)我來(lái)答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問(wèn)嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問(wèn)解千愁!


 
             
             
             
             
             
             
             
             
                     
                     
                     
                     
                     
                    