PMP認證考試練習題及參考答案(二十八)
1 A task-oriented family tree of activities is a: 
A Detailed plan. 
B Linear responsibility chart. 
C Work breakdown structure. 
D Cost account coding system. 
E Work package description. 
ans:C 
2 Management plans include all of the following except: 
A Organization of project. 
B Job descriptions. 
C Policies and procedures. 
D Linear responsibility charts. http://ks.examda.com
E Scope baseline. 
ans:E 
3 A comprehensive definition of scope management would be: 
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project. 
B Approval of the scope baseline. 
C Approval of the detailed project charter. 
D Configuration control. 
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship. 
ans:A 
4 The process of choosing/documenting the best approach to achieve the project objectives is part of: 
A The scope baseline. 
B Scope authorization 
C Scope definition 來源:考試大
D Scope planning. 
E All of the above. 
ans:D 
5 A completion of a local government study resides on your critical path. This would most likely be referred to as: 
A Soft logic 
B Hard logic 
C An external dependency 
D A mandatory dependency 
E A lost cause 
ans:C 
6 Which of the following can affect network durations? 
A Skills of the resource pool 
B Calendar dates 
C Constraints 
D All of the above 
E A and B only 
ans:E 
7 Sources for data on activity durations and resource requirements can be gathered from which of the following: 
A Past project records (historical data) 
B Commercial techniques (standard practices, rules of thumb) 
C Past project team members knowledge (experience, oldtimers) 
D All of the above www.Examda.CoM
E A and C only 
ans:D 
8 The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency. 
A Discretionary 
B Mandatory 
C External 
D Soft logic 
E Subcontracted 
ans:B 
9 "Hard logic" in the preparation of a network refers to: 
A Discretionay dependencies 
B External depenencies 
C Mandatory dependencies 
D All of the above 
E A abd B only 
ans:C 
10 The difference between a project and a program is that: 
A A program is made up of multiple projects 
B A program requires at least three times longer to plan than a project 
C A project is a one-shot deal while a program is on-going 
D A and C 
E B and C 
ans:D 
11 As a control tool, the bar chart (Gantt) methods is most beneficial for: 
A rearranging conflicting tasks 
B depicting actual versus planned tasks 
C showing the outer dependencies of tasks 
D A and C. 
E A and D 
ans:B 
12 You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should: 
A Immediately inform the sponsor and ask for advice 
B Do nothing until the slippage occurs 
C See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis 
D Look for someone to blame before you see the sponsor 
E Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation 
ans:C 


 
             
             