  PMP考試全真模擬題及答案(樣題)

  1.Which of the following is true about accuracy and precision?

  A. Precision is consistency and accuracy is correctness

  B.Precision is correctness and accuracy is consistency

  C.Precision and accuracy are same

  D. Precision is used for measuring length and accuracy is used for time measurements Your

  下列哪個關于正確度和精確度的說法是正確的?

  A.精確度是說連續(xù)性;正確度是說是否符合事實

  B.精確度是說是否符合事實;正確度是說連續(xù)性

  C.精確度和正確度是一樣的

  D.精確度用來測量長度;正確度用來測量你的時間

  答案:A 參考:PMBOK2004 CH P154

  2.Which process group is associated with schedule control, scope control, and cost control

  A. Monitoring and Controlling

  B. Planning

  C. Executing

  D. Closing

  哪個過程組包括進度控制,范圍控制和成本控制?

  A.監(jiān)控項目

  B.規(guī)劃

  C.執(zhí)行

  D.收尾

  答案:A 參考:PMBOK2004 CH P58

  3.In Probability and Impact Metrics which of the following statement is true?

  A. For opportunities, the high risk (dark grey) zone offers greatest benefits

  B. For opportunities, the low risk (medium grey) zone offers lowest risk and best benefits

  C. for Risks the high risk (dark grey) zone offers greatest benefits

  D. for Risks the low risk (medium grey) zone should be addressed first

  關于概率和影響矩陣,下列哪個說法是正確的?

  A.對機會而言,高風險(黑灰色)區(qū)域意味著代表最大的利益

  B.對機會而言,低風險(中灰色)區(qū)域意味著最低的風險和最好的利益

  C.對風險而言,高風險(黑灰色)區(qū)域意味著最大的利益

  D.對風險而言,低風險(中灰色)區(qū)域應該必須首先確定

  答案:A 參考:PMBOK2004 CH P210

  4.Zero defects practice or Do it first time is associated with which of the following?

  A. Crosby

  B. Juran

  C. Deming

  D. Shewhart

  零缺陷或者事情一次作對和下列哪個有關?

  A.克勞斯比

  B.朱蘭

  C.戴明

  D.休哈特

  答案:A

  5.Which of the following would be the BEST description of project management plan?

  A. It contains risk, cost, process improvement and other management plans.

  B. It is one of the outputs of project management software.

  C. it is milestone.

  D. it is project scope statement.

  下列哪個最好的描述了項目管理計劃?

  A.包括風險、成本、過程改進和其他管理計劃

  B.是項目管理軟件的輸出之一

  C.是里程碑

  D.是項目范圍說明書

  答案:A 解釋:用排除法,選一個相對合適的,注意選項B項目管理軟件不等于項目管理信息系統(tǒng)

  6.Purchase order is the simplest example of _________ type of contract

  A.T&M Contract

  B. Fixed Price

  C. Cost plus Incentive Fee

  D. Cost plus Fixed Fee

  采購單是什么類型合同的例子?

  A.時間材料合同

  B.固定價格

  C.成本加獎勵費用

  D.成本加固定費用

  答案:B 參考:PMBOK2004 CH P230(仔細看能找到原文)

  7.You are the project manager in East West Construction Company. After the completion of the structure you are visiting the site and checking whether the construction is as per the plan by taking the measurements. This is an example of

  A. Risk Identification to prevent issues in the future

  B. Active project management

  C. Quality Assurance activity - Prevention

  D. Quality Control Activity - Inspection

  你是東西建筑公司的項目經(jīng)理。在完成建筑后,你到實施地點檢查是否建筑按照計劃進行了測量。這是什么的例子?

  A.風險識別用來防止未來出現(xiàn)的問題;

  B.動態(tài)項目管理

  C.質(zhì)量保證活動-預防

  D.質(zhì)量控制活動-檢查

  答案:D 解釋:檢查作為工具出現(xiàn)在兩個過程,范圍核實和質(zhì)量控制

  8.You are in charge of installing a Voice Response System for a major company. You are about to start preparing the estimates and the Sponsor informed you that the estimate should be as much close to reality as possible. Which of the following you will most likely to use for your estimation:

  A.CPM

  B.PERT

  C.PDM

  D. Monte Carlo Simulation

  你在負責為某個大公司安裝聲音回傳系統(tǒng)。你開始準備估算時出資人告訴你估算必須盡可能接近實際。你最可能使用下列哪個做你的估算?

  A.CPM

  B.PERT

  C.PDM

  D.蒙特卡羅模擬

  答案:D 解釋:蒙特卡羅運用統(tǒng)計學進行模擬,相對而言比較貼近實際,也可以排除A和C都不是估算,選項B是缺乏經(jīng)驗的時候使用的,最沒譜。

  9.Create WBS is part which Knowledge Area?

  A. Project Scope Management

  B. Project Time Management

  C. Project Integration Management

  D. Project Cost Management

  創(chuàng)建WBS是哪個知識領域的一部分

  A.項目范圍管理

  B.項目時間管理

  C.項目整體管理

  D.項目成本管理

  答案:A

  10.If the optimistic estimate for an activity is 18 and standard deviation is 3. If the Most likely estimate is 30, the chance the activity will be finished between 23 and 35 days is

  A.95.44

  B.68.26

  C.99.73

  D.99.999

  如果某個活動的樂觀估計是18天,標準差是3。如果最可能估計是30天,這個活動在23天到35天之間完成的概率是?

  A.95.44

  B.68.26

  C.99.73

  D.99.999

  答案:A 解釋:這個活動的最悲觀估計 X,(X-18)/6=3;所以最悲觀是36;平均估算值=(54+120)/6=29;23到35,剛好左右各兩個標準差,概率為95.44%

  相關推薦:

  2011年PMP模擬習題匯總(附參考答案)

  PMP考試模擬試題

發(fā)布:2007-03-02 10:46    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件